What is the lead in times for Sesame lifts?
We normally estimate between six to seven months. Working close to the architect and customer our access lifts take approximately eight weeks to design, ten weeks for parts to be manufactured, nine weeks to assemble and quality control, and two weeks to be installed on your premises.
We allow one week as a contingency between each stage. If you require a shorter time frame, please talk to us and we can see what’s possible.