Lift Installation
With over 20 years of experience, Sesame Access has developed in conjunction with our partner companies the following procedure to ensure a two-week lift installation and prompt handover. Deviations from the following steps may result in delays to the installation and practical completion dates.
1) The lift pit
- Pre-install inspection of the pit must take place a minimum of one week before install
- Sesame cannot inspect the pit until it is finished with all gridlines and datums
- The pit must be clean, and clear of all debris and other trades
- Delivery and installation details will be covered
- See "Pre-Install Checklist" below
Pit drawing, Click to enlarge
2) Lift delivery and install
- The trim/lining of the pit arrives first and is fixed and levelled
- The Sesame lift will be delivered via HIAB and if possible, lowered directly into the pit
- If the HIAB cannot lower into the pit, a gantry crane will be used to traverse the lift into position
- Once in place, Sesame engineers will install the lift and get it up and running
- See below "Pit-Trim Sign Off", "Standard Install RAMS" and "Data Sheets"
Lift transporting by HIAB
3) Cladding and commissioning
- The cladding must be cut to size, and permanent power must be on site to begin the second week
- Sesame will supervise the cladding of the lift, to ensure all requirements and standards are met
- The final installation steps, including commissioning and testing
Cladding Samples - Click to Enlarge
4) Handover
- All handover and testing documents are issued from the Sesame head office
- The client must receive training on correct and safe lift operation
- All Sesame lifts come with a 1 year warranty, and one standard service after 6-months.
- Click here for service details
Downloads
PDF 387.44KB
PDF 681.69KB
PDF 1.61MB